Connecting Visaginas NPP to Transmission Grid
This project implemented by Visagino atominė elektrinė, UAB is aimed at preparing the infrastructure of electrical network required for connecting the new Visaginas NPP to the transmission grid.
Visaginas NPP will be connected to the transmission grid in three stages (the project is due to be accomplished in 2015):
- During the 1st stage, the pre-project studies will be prepared, scientific research will be conducted;
- During the 2nd stage, the technical project will be drawn up for the reconstruction of 330/110 kV substation;
- During the 3rd stage, the reconstruction of 330/110 kV substation will take place.
The first stage of the project is already completed. In 2010 the study that analysed what the scheme of the substation should be and in what stages it should be reconstructed so that electricity could be continuously supplied to the old Ignalina NPP, its consumers in construction sector and the new Visaginas NPP could be connected to it was completed. During the first stage, a piece of research “Distribution of Overvoltage in 330/110 kV Substation of Visaginas NPP” was prepared.